Pulp 2 Release Planning » History » Revision 1
Revision 1/28
| Next »
bmbouter, 02/26/2018 08:23 PM
Initial content
Pulp 2 Release Planning¶
This serves as a step-by-step guide to coordinating a Pulp 2 release. This is mostly about facilitating the required communication to keep everyone on the same page.
1. Identify that a release needs to happen via pulp-dev. This can be something that is requested by anyone who wants to release bits that have been merged.
2. Create a Release Planning Page specific for that release. For example here is the 2.15.3 release Status page. At a minimum it should contain the following:
- dev freeze date
- tentative beta date
- tentative RC date (only for Y releases, not Z releases)
- tentative GA date
3. Link to the new page made in step (2) from the overall Release Schedule.
4. Communicate the dev feeze datetime to pulp-dev with a link to the new release schedule.
Updated by bmbouter over 6 years ago · 1 revisions