Project

Profile

Help

Actions

2170 Release Schedule » History » Revision 15

« Previous | Revision 15/18 (diff) | Next »
ipanova@redhat.com, 08/23/2018 06:27 PM


2.17.0 Release Schedule

The current tentative release date for 2.17.0 is August 30, 2018

Checklist

The first item on the list not struck through is in progress.

  • Dev Freeze date
  • Beta Build date.
    • August 14, 2018
  • Prerequisites to building:
    • -Issues blocking release
    • -No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar)
  • -master branch now tracks development for next Y release
  • -build system adapted to build from new dev branch
  • -test scratch build from beta branch
  • -beta is built from release branch
  • waiting period (1 week after beta release date) before RC
    • -RC Date: August 23, 2018
  • waiting period (1 week after RC release date) before GA
    • -GA Date: August 30, 2018
  • verify issues with "verification required" set

The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 2.17.0 release progresses. See the Release Schedule for more details.

If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available August 30, 2018. This page will be updated as progress is made.

Release Contact: asmacdo on freenode (#pulp and#pulp-dev)

Updated by ipanova@redhat.com over 5 years ago · 15 revisions