Project

Profile

Help

Issue #2734

closed

task group never quite finishes if pulp is restarted in the middle of task run

Added by cduryee over 7 years ago. Updated over 5 years ago.

Status:
CLOSED - CURRENTRELEASE
Priority:
High
Assignee:
Category:
-
Sprint/Milestone:
-
Start date:
Due date:
Estimated time:
Severity:
2. Medium
Version:
Platform Release:
2.14.1
OS:
Triaged:
Yes
Groomed:
No
Sprint Candidate:
Yes
Tags:
Pulp 2
Sprint:
Sprint 24
Quarter:

Description

NOTE: this bug was found in a product that uses pulp 2.8. I have not yet reproduced w/ plain pulp.

If you cancel a task in a task group, it appears that the task group is not updated.

For example:

  • create a task group with many applicability regeneration tasks
  • cancel tasks directly via `pulp-admin task cancel`

At this point, the task group should say that all the tasks are cancelled. However, it will show the tasks as in 'waiting' state still.


Related issues

Related to Pulp - Issue #2835: Tasks stuck in waiting after restart of pulp servicesCLOSED - CURRENTRELEASEdalleyActions
Related to Pulp - Issue #2861: Queued tasks will be lost if the resource manager is restarted via systemctlCLOSED - WONTFIXdaviddavisActions

Also available in: Atom PDF