Sprint Plans » History » Sprint/Milestone 8

rchan, 05/30/2018 03:07 PM

1 1 rchan
# Sprint Plans
2
3 8 rchan
## Sprint 38
4
5
Dates: Friday June 1, 2018 - Thursday June 21, 2018  
6
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
7
Notes
8
9
  - Pulp 2 bugs/features:
10
11
>   - FIPS
12
>   - Modularity
13
>   - Container/Docker plugin enhancements?
14
15
  - Core GA Features:
16
17
>   - start implementation of Lazy sync
18
19
  - Continued progress on RPM and Docker Plugins
20
21 7 rchan
## Sprint 37
22
23
Dates: Friday May 11, 2018- Thursday May 31,2018  
24
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
25
Notes
26
27
  - Reserve time for fixing issues found after Core Beta released
28
  - Planning for conferences and Pulp 3.0 GA planning
29
30 5 rchan
## Sprint 36
31
32
Dates: Friday April 20, 2018- Thursday May 10,2018  
33
Sprint Goals/Focus: Pulp 3 Core Beta  
34
Notes
35
36
  - Items focused on remaining Pulp 3.0 Core Beta deliverables
37 6 rchan
  - Reserve time for fixing issues found after Core Beta released
38
  - Planning for conferences and Pulp 3.0 GA planning
39 5 rchan
40
## Sprint 35
41
42
Dates: Friday March 30, 2018- Thursday April 19,2018  
43
Sprint Goals/Focus: Pulp 3 Core Beta  
44
Notes
45
46
  - Items focused on Pulp 3.0 Core Beta deliverables
47
48 3 rchan
## Sprint 34
49
50 4 rchan
Dates: Friday March 9, 2018- Thursday March 29,2018  
51 1 rchan
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze  
52
Notes
53
54
  - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. 
55
  - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
56 4 rchan
  - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.