Project

Profile

Help

Sprint Plans » History » Sprint/Milestone 7

rchan, 05/11/2018 02:51 PM

1 1 rchan
# Sprint Plans
2
3 7 rchan
## Sprint 37
4
5
Dates: Friday May 11, 2018- Thursday May 31,2018  
6
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
7
Notes
8
9
  - Reserve time for fixing issues found after Core Beta released
10
  - Planning for conferences and Pulp 3.0 GA planning
11
12 5 rchan
## Sprint 36
13
14
Dates: Friday April 20, 2018- Thursday May 10,2018  
15
Sprint Goals/Focus: Pulp 3 Core Beta  
16
Notes
17
18
  - Items focused on remaining Pulp 3.0 Core Beta deliverables
19 6 rchan
  - Reserve time for fixing issues found after Core Beta released
20
  - Planning for conferences and Pulp 3.0 GA planning
21 5 rchan
22
## Sprint 35
23
24
Dates: Friday March 30, 2018- Thursday April 19,2018  
25
Sprint Goals/Focus: Pulp 3 Core Beta  
26
Notes
27
28
  - Items focused on Pulp 3.0 Core Beta deliverables
29
30 3 rchan
## Sprint 34
31
32 4 rchan
Dates: Friday March 9, 2018- Thursday March 29,2018  
33 1 rchan
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze  
34
Notes
35
36
  - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. 
37
  - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
38 4 rchan
  - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.