# Sprint Plans
2
3 58 rchan
## Sprint 50
4
5
Dates: Friday Mar 8, 2019 - Thursday 28-Mar-2019  
6
Sprint Goals/Focus: Pulp 3 RC + Plugins to Core RC feature parity  
7
Notes
8
9
  - pulplift working without issues
10
  - Pulp3 Core RC Features:
11
      - Documentation work
12 62 rchan
      - Stages API bug fixes
13 58 rchan
      - RC blockers
14
          - https://pulp.plan.io/issues?query_id=121
15
      - Fix blockers for Ansible Galaxy team
16
          - bugs
17
          - Unit testing
18 61 rchan
  - Pulp 3 Docker/RPM/Python/Ansible Plugin
19 60 rchan
      - Working with Pulp 3 Core RC release
20
      - Bug fixes discovered post beta
21 58 rchan
  - Pulp 2 bugs/features:
22
      - must fix/urgent bugs (planned feature work for 2.19.0 completed)
23
24 50 rchan
## Sprint 49
25
26
Dates: Friday Feb 15, 2019 - Thursday 7-Mar-2019  
27
Sprint Goals/Focus: Pulp 3 RC + Plugins to Core RC feature parity  
28
Notes
29
30 56 rchan
  - pulplift working without issues
31 53 ipanova@redhat.com
  - Pulp3 Core RC Features:
32
      - ~~Lazy sync completed~~
33 1 rchan
      - UUID work
34
      - Documentation work
35 55 rchan
      - Stages API improvements
36 1 rchan
      - RC blockers
37
          - https://pulp.plan.io/issues?query_id=121
38 55 rchan
      - Fix blockers for Ansible Galaxy team
39
          - bugs
40
          - Unit testing
41 57 rchan
  - Pulp 3 Docker/RPM Plugin
42
      - Just enough work to keep these working with changes to core on master branch
43
      - note: feature parity with core RC will be done at a later time 
44 50 rchan
  - Pulp 2 bugs/features:
45
      - must fix/urgent bugs (planned feature work for 2.19.0 completed)
46
47 41 rchan
## Sprint 48
48
49
Dates: Friday Jan 25, 2019 - Thursday 14-Feb-2019  
50 48 rchan
Sprint Goals/Focus: Pulp3 RC  
51 47 rchan
Notes  
52
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta  
53 41 rchan
Notes
54 47 rchan
55
  - Pulp3 Core RC Features:
56
      - Lazy sync completed
57
      - UUID work
58
      - Documentation work
59
      - Stages API improvements
60
          - Docker sync rework
61
      - RC blockers
62
          - https://pulp.plan.io/issues?query_id=121
63
  - Pulp 2 bugs/features:
64
      - bugs as prioritized by internal stakeholders
65 41 rchan
66
## Sprint 47
67
68
Dates: Friday Jan 04, 2019 - Thursday 24-Jan-2019  
69
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta  
70
Notes
71
72
  - Pulp 2 bugs/features:
73 1 rchan
      - bugs as prioritized by internal stakeholders
74 41 rchan
      - Pulp 2.19.0:
75 49 rchan
          - Module Errata Depsolving - reconcile plan/strategy & complete merge
76 43 rchan
  - Pulp3 Core RC Features:
77 42 rchan
      - Lazy sync completed
78 43 rchan
      - UUID work
79 1 rchan
      - Content protection work
80
      - Documentation work
81 43 rchan
      - Stages API improvements
82
          - Docker sync rework
83
      - RC blockers
84 45 daviddavis
          - https://pulp.plan.io/issues?query_id=121
85 46 rchan
  - Docker beta
86
  - RPM plugin
87
      - Kickstart tree planning
88 41 rchan
89 36 rchan
## Sprint 46
90 35 rchan
91 36 rchan
Dates: Wednesday Nov 29, 2018 - Wednesday 20-Dec-2018  
92 40 rchan
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta  
93
Notes
94 1 rchan
95 40 rchan
  - Pulp 2 bugs/features:
96
      - bugs as prioritized by internal stakeholders
97
      - Pulp 2.19.0:
98
          - Module Errata Depsolving
99
  - Pulp3 Core GA Features:
100
      - Lazy sync completed (https://pulp.plan.io/issues/3693)
101
      - Docker publish
102
      - Single Content work
103
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
104
      - Content protection work
105
      - Documentation work
106
      - Katello P1 - migrations
107 38 rchan
108 36 rchan
## Sprint 45
109 1 rchan
110 35 rchan
Dates: Friday Nov 2, 2018 - Tuesday 28-Nov-2018  
111 34 rchan
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC  
112
Notes
113
114 1 rchan
  - Pulp 2 bugs/features:
115 34 rchan
      - bugs as prioritized by internal stakeholders
116 37 rchan
      - 2.18.0 Module Errata Applicability
117
      - Module Errata Depsolving
118 34 rchan
  - Pulp3 Core GA Features:
119
      - Lazy sync continues (https://pulp.plan.io/issues/3693)
120
      - RPM plugin beta release
121 1 rchan
      - Docker sync + publish
122 38 rchan
      - Single Content work
123 1 rchan
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
124 38 rchan
      - Content protection work
125 39 rchan
      - Documentation work
126 35 rchan
127
## Sprint 44
128
129
Dates: Friday Oct 5, 2018 - Thursday ~~Oct 26~~ 01-Nov, 2018  
130
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC  
131
Notes
132
133
  - Pulp 2 bugs/features:
134
      - bugs as prioritized by internal stakeholders
135
      - 2.19.0 Module Errata Applicability & Depsolving
136
  - Pulp3 Core GA Features:
137
      - Lazy sync continues (https://pulp.plan.io/issues/3693)
138 1 rchan
      - RPM plugin beta release
139 35 rchan
      - Docker sync + publish
140
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
141 38 rchan
      - Content protection work
142 35 rchan
      - Katello P1 items (e.g.?)  
143 34 rchan
        Decided to extend sprint through week after on-sight planning meeting to prep for next Sprint.
144 31 rchan
145
## Sprint 43
146 1 rchan
147 34 rchan
Dates: Friday Sept 14, 2018 - Thursday Oct 4, 2018  
148 1 rchan
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC  
149 31 rchan
Notes
150 34 rchan
151
  - Pulp 2 bugs/features:  
152 31 rchan
    ~~\*\* 2.18.0 Module Errata support~~
153
      - bugs as prioritized by internal stakeholders
154
      - 2.19.0 Module Errata Applicability & Depsolving
155 32 daviddavis
  - Pulp3 Core GA Features:
156
      - Lazy sync continues (https://pulp.plan.io/issues/3693)
157 33 ipanova@redhat.com
      - RPM plugin beta release
158 31 rchan
      - Docker plugin (models) + sync
159 32 daviddavis
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
160
      - Content protection work (https://pulp.plan.io/issues/3968)
161
      - Katello P1 items (e.g. https://pulp.plan.io/issues/3802)
162 31 rchan
      - Installer wrap up
163 26 rchan
164
## Sprint 42
165 30 rchan
166 26 rchan
Dates: Friday Aug 24, 2018 - Thursday Sept 13, 2018  
167
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
168
Notes
169
170 27 rchan
  - Pulp 2 bugs/features:
171
      - 2.18.0 Module Errata support
172 26 rchan
      - bugs as prioritized by internal stakeholders
173
  - Pulp3 Core GA Features:
174 30 rchan
      - Lazy sync start this sprint (https://pulp.plan.io/issues/3693)
175 27 rchan
      - ~~RPM plugin (sync +~~ publish) 
176 26 rchan
      - Docker plugin (models)
177 28 daviddavis
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
178 26 rchan
      - ~~CLI progress~~ keep #3627 on sprint, this is blocked until bindings id/href is resolved- 
179 30 rchan
      - bindings id/href resolution - off-sprint prototype from @bizhang will unblock:
180
          - ~~3851, 3856, 3580,~~ 3836
181
      - Installer work - 1 FTE during this sprint  
182 26 rchan
        ~~\* Merge & complete docs tasks that have been partially complete for some time.~~
183 20 rchan
184
## Sprint 41
185
186
Dates: Friday Aug 3, 2018 - Thursday August 23, 2018  
187
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
188
Notes
189
190
  - Pulp 2 bugs/features:
191
      - Module Errata support
192
      - bugs as prioritized by Sat liasons
193 22 bizhang
  - Core GA Features:
194 24 rchan
      - CLI progress- keep #3627 on sprint, this is blocked until bindings id/href is resolved 
195
      - bindings id/href resolution - off-sprint prototype from @bizhang will unblock:
196 21 bmbouter
          - 3851, 3856, 3580, 3836
197
      - Installer work on sprint - 0.5 FTE starting on Aug 20th
198 20 rchan
      - Lazy sync start this sprint (https://pulp.plan.io/issues/3693)
199 21 bmbouter
      - Pulp 3 RPM (sync+publish) and Docker( models) Plugins on start again
200 20 rchan
      - Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
201 14 rchan
202
## Sprint 40
203
204
Dates: Friday July 13, 2018 - Thursday August 2, 2018  
205
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
206
Notes
207
208
  - Pulp 2 bugs/features:
209
      - Pulp 2.17 features:
210 18 milan
          - Rich Dependency Support
211 14 rchan
              - Weak dependencies? (see Issue #3847)
212
          - Advanced Modularity
213
          - Container/Docker plugin enhancements (3137)
214 15 rchan
  - Core GA Features:
215 19 bmbouter
      - CLI progress - feedback from July 2 deadline digested
216 14 rchan
      - Declarative Versions - waiting on input after deep dive, then https://pulp.plan.io/issues/3844
217 17 rchan
      - Installer work on sprint - no commitment from core team on staffing
218
      - Lazy sync still on hold. Let's focus on less & know this is ready to start.
219
      - Pulp 3 RPM and Docker Plugins on hold (again, focus on less & get done before start this again)
220 14 rchan
      - Performance bugs if staffing available - some of this is already in progress
221 12 rchan
222
## Sprint 39
223
224
Dates: Friday June 22, 2018 - Thursday July 12, 2018  
225
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
226
Notes
227
228
  - Pulp 2 bugs/features:
229
      - FIPS - can we aim to close all known stories that aren't blocked?
230
      - Pulp 2.17 features:
231
          - Advanced Modularity + Rich Dependency Support
232
          - Container/Docker plugin enhancements
233
  - Core GA Features:
234
      - Installer work on sprint - no commitment from core team on staffing
235 13 rchan
      - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
236
      - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested
237 12 rchan
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution
238 8 rchan
239
## Sprint 38
240
241
Dates: Friday June 1, 2018 - Thursday June 21, 2018  
242
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
243
Notes
244
245 9 rchan
  - Pulp 2 bugs/features:
246
      - FIPS
247 10 rchan
      - Modularity
248 1 rchan
      - Container/Docker plugin enhancements
249 10 rchan
  - Core GA Features:
250
      - Installerwork on sprint - no commitment from core team on staffing
251 11 rchan
  - Pause progress on Pulp 3 RPM and Docker Plugins
252
      - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint
253 8 rchan
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well
254 7 rchan
255
## Sprint 37
256
257
Dates: Friday May 11, 2018- Thursday May 31,2018  
258
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
259 1 rchan
Notes
260
261
  - Reserve time for fixing issues found after Core Beta released
262 10 rchan
  - Planning for conferences and Pulp 3.0 GA planning
263
264
Completion
265
266 7 rchan
  - Lazy Sync planning completed
267 5 rchan
268
## Sprint 36
269
270
Dates: Friday April 20, 2018- Thursday May 10,2018  
271
Sprint Goals/Focus: Pulp 3 Core Beta  
272
Notes
273
274 6 rchan
  - Items focused on remaining Pulp 3.0 Core Beta deliverables
275
  - Reserve time for fixing issues found after Core Beta released
276 5 rchan
  - Planning for conferences and Pulp 3.0 GA planning
277
278
## Sprint 35
279
280
Dates: Friday March 30, 2018- Thursday April 19,2018  
281
Sprint Goals/Focus: Pulp 3 Core Beta  
282
Notes
283
284
  - Items focused on Pulp 3.0 Core Beta deliverables
285 3 rchan
286
## Sprint 34
287 4 rchan
288 1 rchan
Dates: Friday March 9, 2018- Thursday March 29,2018  
289
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze  
290
Notes
291
292
  - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. 
293 4 rchan
  - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
294 1 rchan
  - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.