Sprint Plans » History » Sprint/Milestone 6
rchan, 04/20/2018 03:53 PM
1 | 1 | rchan | # Sprint Plans |
---|---|---|---|
2 | |||
3 | 5 | rchan | ## Sprint 36 |
4 | |||
5 | Dates: Friday April 20, 2018- Thursday May 10,2018 |
||
6 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
7 | Notes |
||
8 | |||
9 | - Items focused on remaining Pulp 3.0 Core Beta deliverables |
||
10 | 6 | rchan | - Reserve time for fixing issues found after Core Beta released |
11 | - Planning for conferences and Pulp 3.0 GA planning |
||
12 | 5 | rchan | |
13 | ## Sprint 35 |
||
14 | |||
15 | Dates: Friday March 30, 2018- Thursday April 19,2018 |
||
16 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
17 | Notes |
||
18 | |||
19 | - Items focused on Pulp 3.0 Core Beta deliverables |
||
20 | |||
21 | 3 | rchan | ## Sprint 34 |
22 | |||
23 | 4 | rchan | Dates: Friday March 9, 2018- Thursday March 29,2018 |
24 | 1 | rchan | Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze |
25 | Notes |
||
26 | |||
27 | - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. |
||
28 | - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag" |
||
29 | 4 | rchan | - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18. |