Sprint Plans » History » Sprint/Milestone 46
rchan, 01/04/2019 03:21 PM
1 | 1 | rchan | # Sprint Plans |
---|---|---|---|
2 | |||
3 | 41 | rchan | ## Sprint 48 |
4 | |||
5 | Dates: Friday Jan 25, 2019 - Thursday 14-Feb-2019 |
||
6 | Sprint Goals/Focus: \<TBD\> |
||
7 | Notes |
||
8 | |||
9 | ## Sprint 47 |
||
10 | |||
11 | Dates: Friday Jan 04, 2019 - Thursday 24-Jan-2019 |
||
12 | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta |
||
13 | Notes |
||
14 | |||
15 | - Pulp 2 bugs/features: |
||
16 | - bugs as prioritized by internal stakeholders |
||
17 | - Pulp 2.19.0: |
||
18 | 43 | rchan | - Module Errata Depsolving - reconcile plan with current work completed |
19 | - Pulp3 Core RC Features: |
||
20 | 42 | rchan | - Lazy sync completed |
21 | 43 | rchan | - UUID work |
22 | 1 | rchan | - Content protection work |
23 | - Documentation work |
||
24 | 43 | rchan | - Stages API improvements |
25 | - Docker sync rework |
||
26 | - RC blockers |
||
27 | 45 | daviddavis | - https://pulp.plan.io/issues?query_id=121 |
28 | 46 | rchan | - Docker beta |
29 | - RPM plugin |
||
30 | - Kickstart tree planning |
||
31 | 41 | rchan | |
32 | 36 | rchan | ## Sprint 46 |
33 | 35 | rchan | |
34 | 36 | rchan | Dates: Wednesday Nov 29, 2018 - Wednesday 20-Dec-2018 |
35 | 40 | rchan | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta |
36 | Notes |
||
37 | 1 | rchan | |
38 | 40 | rchan | - Pulp 2 bugs/features: |
39 | - bugs as prioritized by internal stakeholders |
||
40 | - Pulp 2.19.0: |
||
41 | - Module Errata Depsolving |
||
42 | - Pulp3 Core GA Features: |
||
43 | - Lazy sync completed (https://pulp.plan.io/issues/3693) |
||
44 | - Docker publish |
||
45 | - Single Content work |
||
46 | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
||
47 | - Content protection work |
||
48 | - Documentation work |
||
49 | - Katello P1 - migrations |
||
50 | 38 | rchan | |
51 | 36 | rchan | ## Sprint 45 |
52 | 1 | rchan | |
53 | 35 | rchan | Dates: Friday Nov 2, 2018 - Tuesday 28-Nov-2018 |
54 | 34 | rchan | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC |
55 | Notes |
||
56 | |||
57 | 1 | rchan | - Pulp 2 bugs/features: |
58 | 34 | rchan | - bugs as prioritized by internal stakeholders |
59 | 37 | rchan | - 2.18.0 Module Errata Applicability |
60 | - Module Errata Depsolving |
||
61 | 34 | rchan | - Pulp3 Core GA Features: |
62 | - Lazy sync continues (https://pulp.plan.io/issues/3693) |
||
63 | - RPM plugin beta release |
||
64 | 1 | rchan | - Docker sync + publish |
65 | 38 | rchan | - Single Content work |
66 | 1 | rchan | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
67 | 38 | rchan | - Content protection work |
68 | 39 | rchan | - Documentation work |
69 | 35 | rchan | |
70 | ## Sprint 44 |
||
71 | |||
72 | Dates: Friday Oct 5, 2018 - Thursday ~~Oct 26~~ 01-Nov, 2018 |
||
73 | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC |
||
74 | Notes |
||
75 | |||
76 | - Pulp 2 bugs/features: |
||
77 | - bugs as prioritized by internal stakeholders |
||
78 | - 2.19.0 Module Errata Applicability & Depsolving |
||
79 | - Pulp3 Core GA Features: |
||
80 | - Lazy sync continues (https://pulp.plan.io/issues/3693) |
||
81 | 1 | rchan | - RPM plugin beta release |
82 | 35 | rchan | - Docker sync + publish |
83 | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
||
84 | 38 | rchan | - Content protection work |
85 | 35 | rchan | - Katello P1 items (e.g.?) |
86 | 34 | rchan | Decided to extend sprint through week after on-sight planning meeting to prep for next Sprint. |
87 | 31 | rchan | |
88 | ## Sprint 43 |
||
89 | 1 | rchan | |
90 | 34 | rchan | Dates: Friday Sept 14, 2018 - Thursday Oct 4, 2018 |
91 | 1 | rchan | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC |
92 | 31 | rchan | Notes |
93 | 34 | rchan | |
94 | - Pulp 2 bugs/features: |
||
95 | 31 | rchan | ~~\*\* 2.18.0 Module Errata support~~ |
96 | - bugs as prioritized by internal stakeholders |
||
97 | - 2.19.0 Module Errata Applicability & Depsolving |
||
98 | 32 | daviddavis | - Pulp3 Core GA Features: |
99 | - Lazy sync continues (https://pulp.plan.io/issues/3693) |
||
100 | 33 | ipanova@redhat.com | - RPM plugin beta release |
101 | 31 | rchan | - Docker plugin (models) + sync |
102 | 32 | daviddavis | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
103 | - Content protection work (https://pulp.plan.io/issues/3968) |
||
104 | - Katello P1 items (e.g. https://pulp.plan.io/issues/3802) |
||
105 | 31 | rchan | - Installer wrap up |
106 | 26 | rchan | |
107 | ## Sprint 42 |
||
108 | 30 | rchan | |
109 | 26 | rchan | Dates: Friday Aug 24, 2018 - Thursday Sept 13, 2018 |
110 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
111 | Notes |
||
112 | |||
113 | 27 | rchan | - Pulp 2 bugs/features: |
114 | - 2.18.0 Module Errata support |
||
115 | 26 | rchan | - bugs as prioritized by internal stakeholders |
116 | - Pulp3 Core GA Features: |
||
117 | 30 | rchan | - Lazy sync start this sprint (https://pulp.plan.io/issues/3693) |
118 | 27 | rchan | - ~~RPM plugin (sync +~~ publish) |
119 | 26 | rchan | - Docker plugin (models) |
120 | 28 | daviddavis | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
121 | 26 | rchan | - ~~CLI progress~~ keep #3627 on sprint, this is blocked until bindings id/href is resolved- |
122 | 30 | rchan | - bindings id/href resolution - off-sprint prototype from @bizhang will unblock: |
123 | - ~~3851, 3856, 3580,~~ 3836 |
||
124 | - Installer work - 1 FTE during this sprint |
||
125 | 26 | rchan | ~~\* Merge & complete docs tasks that have been partially complete for some time.~~ |
126 | 20 | rchan | |
127 | ## Sprint 41 |
||
128 | |||
129 | Dates: Friday Aug 3, 2018 - Thursday August 23, 2018 |
||
130 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
131 | Notes |
||
132 | |||
133 | - Pulp 2 bugs/features: |
||
134 | - Module Errata support |
||
135 | - bugs as prioritized by Sat liasons |
||
136 | 22 | bizhang | - Core GA Features: |
137 | 24 | rchan | - CLI progress- keep #3627 on sprint, this is blocked until bindings id/href is resolved |
138 | - bindings id/href resolution - off-sprint prototype from @bizhang will unblock: |
||
139 | 21 | bmbouter | - 3851, 3856, 3580, 3836 |
140 | - Installer work on sprint - 0.5 FTE starting on Aug 20th |
||
141 | 20 | rchan | - Lazy sync start this sprint (https://pulp.plan.io/issues/3693) |
142 | 21 | bmbouter | - Pulp 3 RPM (sync+publish) and Docker( models) Plugins on start again |
143 | 20 | rchan | - Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
144 | 14 | rchan | |
145 | ## Sprint 40 |
||
146 | |||
147 | Dates: Friday July 13, 2018 - Thursday August 2, 2018 |
||
148 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
149 | Notes |
||
150 | |||
151 | - Pulp 2 bugs/features: |
||
152 | - Pulp 2.17 features: |
||
153 | 18 | milan | - Rich Dependency Support |
154 | 14 | rchan | - Weak dependencies? (see Issue #3847) |
155 | - Advanced Modularity |
||
156 | - Container/Docker plugin enhancements (3137) |
||
157 | 15 | rchan | - Core GA Features: |
158 | 19 | bmbouter | - CLI progress - feedback from July 2 deadline digested |
159 | 14 | rchan | - Declarative Versions - waiting on input after deep dive, then https://pulp.plan.io/issues/3844 |
160 | 17 | rchan | - Installer work on sprint - no commitment from core team on staffing |
161 | - Lazy sync still on hold. Let's focus on less & know this is ready to start. |
||
162 | - Pulp 3 RPM and Docker Plugins on hold (again, focus on less & get done before start this again) |
||
163 | 14 | rchan | - Performance bugs if staffing available - some of this is already in progress |
164 | 12 | rchan | |
165 | ## Sprint 39 |
||
166 | |||
167 | Dates: Friday June 22, 2018 - Thursday July 12, 2018 |
||
168 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
169 | Notes |
||
170 | |||
171 | - Pulp 2 bugs/features: |
||
172 | - FIPS - can we aim to close all known stories that aren't blocked? |
||
173 | - Pulp 2.17 features: |
||
174 | - Advanced Modularity + Rich Dependency Support |
||
175 | - Container/Docker plugin enhancements |
||
176 | - Core GA Features: |
||
177 | - Installer work on sprint - no commitment from core team on staffing |
||
178 | 13 | rchan | - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins |
179 | - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested |
||
180 | 12 | rchan | - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution |
181 | 8 | rchan | |
182 | ## Sprint 38 |
||
183 | |||
184 | Dates: Friday June 1, 2018 - Thursday June 21, 2018 |
||
185 | Sprint Goals/Focus: Pulp 3 GA + Pulp 2 |
||
186 | Notes |
||
187 | |||
188 | 9 | rchan | - Pulp 2 bugs/features: |
189 | - FIPS |
||
190 | 10 | rchan | - Modularity |
191 | 1 | rchan | - Container/Docker plugin enhancements |
192 | 10 | rchan | - Core GA Features: |
193 | - Installerwork on sprint - no commitment from core team on staffing |
||
194 | 11 | rchan | - Pause progress on Pulp 3 RPM and Docker Plugins |
195 | - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint |
||
196 | 8 | rchan | - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well |
197 | 7 | rchan | |
198 | ## Sprint 37 |
||
199 | |||
200 | Dates: Friday May 11, 2018- Thursday May 31,2018 |
||
201 | Sprint Goals/Focus: Pulp 3 GA + Pulp 2 |
||
202 | 1 | rchan | Notes |
203 | |||
204 | - Reserve time for fixing issues found after Core Beta released |
||
205 | 10 | rchan | - Planning for conferences and Pulp 3.0 GA planning |
206 | |||
207 | Completion |
||
208 | |||
209 | 7 | rchan | - Lazy Sync planning completed |
210 | 5 | rchan | |
211 | ## Sprint 36 |
||
212 | |||
213 | Dates: Friday April 20, 2018- Thursday May 10,2018 |
||
214 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
215 | Notes |
||
216 | |||
217 | 6 | rchan | - Items focused on remaining Pulp 3.0 Core Beta deliverables |
218 | - Reserve time for fixing issues found after Core Beta released |
||
219 | 5 | rchan | - Planning for conferences and Pulp 3.0 GA planning |
220 | |||
221 | ## Sprint 35 |
||
222 | |||
223 | Dates: Friday March 30, 2018- Thursday April 19,2018 |
||
224 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
225 | Notes |
||
226 | |||
227 | - Items focused on Pulp 3.0 Core Beta deliverables |
||
228 | 3 | rchan | |
229 | ## Sprint 34 |
||
230 | 4 | rchan | |
231 | 1 | rchan | Dates: Friday March 9, 2018- Thursday March 29,2018 |
232 | Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze |
||
233 | Notes |
||
234 | |||
235 | - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. |
||