# Sprint Plans
2
3 41 rchan
## Sprint 48
4
5
Dates: Friday Jan 25, 2019 - Thursday 14-Feb-2019  
6
Sprint Goals/Focus: \<TBD\>  
7
Notes
8
9
## Sprint 47
10
11
Dates: Friday Jan 04, 2019 - Thursday 24-Jan-2019  
12
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta  
13
Notes
14
15
  - Pulp 2 bugs/features:
16
      - bugs as prioritized by internal stakeholders
17
      - Pulp 2.19.0:
18
          - Module Errata Depsolving
19
  - Pulp3 Core GA Features:
20
      - Lazy sync completed (https://pulp.plan.io/issues/3693)
21
      - Single Content work
22
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
23
      - Content protection work
24
      - Documentation work
25
      - Docker beta
26
27 36 rchan
## Sprint 46
28 35 rchan
29 36 rchan
Dates: Wednesday Nov 29, 2018 - Wednesday 20-Dec-2018  
30 40 rchan
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta  
31
Notes
32 1 rchan
33 40 rchan
  - Pulp 2 bugs/features:
34
      - bugs as prioritized by internal stakeholders
35
      - Pulp 2.19.0:
36
          - Module Errata Depsolving
37
  - Pulp3 Core GA Features:
38
      - Lazy sync completed (https://pulp.plan.io/issues/3693)
39
      - Docker publish
40
      - Single Content work
41
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
42
      - Content protection work
43
      - Documentation work
44
      - Katello P1 - migrations
45 38 rchan
46 36 rchan
## Sprint 45
47 1 rchan
48 35 rchan
Dates: Friday Nov 2, 2018 - Tuesday 28-Nov-2018  
49 34 rchan
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC  
50
Notes
51
52 1 rchan
  - Pulp 2 bugs/features:
53 34 rchan
      - bugs as prioritized by internal stakeholders
54 37 rchan
      - 2.18.0 Module Errata Applicability
55
      - Module Errata Depsolving
56 34 rchan
  - Pulp3 Core GA Features:
57
      - Lazy sync continues (https://pulp.plan.io/issues/3693)
58
      - RPM plugin beta release
59 1 rchan
      - Docker sync + publish
60 38 rchan
      - Single Content work
61 1 rchan
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
62 38 rchan
      - Content protection work
63 39 rchan
      - Documentation work
64 35 rchan
65
## Sprint 44
66
67
Dates: Friday Oct 5, 2018 - Thursday ~~Oct 26~~ 01-Nov, 2018  
68
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC  
69
Notes
70
71
  - Pulp 2 bugs/features:
72
      - bugs as prioritized by internal stakeholders
73
      - 2.19.0 Module Errata Applicability & Depsolving
74
  - Pulp3 Core GA Features:
75
      - Lazy sync continues (https://pulp.plan.io/issues/3693)
76 1 rchan
      - RPM plugin beta release
77 35 rchan
      - Docker sync + publish
78
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
79 38 rchan
      - Content protection work
80 35 rchan
      - Katello P1 items (e.g.?)  
81 34 rchan
        Decided to extend sprint through week after on-sight planning meeting to prep for next Sprint.
82 31 rchan
83
## Sprint 43
84 1 rchan
85 34 rchan
Dates: Friday Sept 14, 2018 - Thursday Oct 4, 2018  
86 1 rchan
Sprint Goals/Focus: Pulp 2 + Pulp 3 RC  
87 31 rchan
Notes
88 34 rchan
89
  - Pulp 2 bugs/features:  
90 31 rchan
    ~~\*\* 2.18.0 Module Errata support~~
91
      - bugs as prioritized by internal stakeholders
92
      - 2.19.0 Module Errata Applicability & Depsolving
93 32 daviddavis
  - Pulp3 Core GA Features:
94
      - Lazy sync continues (https://pulp.plan.io/issues/3693)
95 33 ipanova@redhat.com
      - RPM plugin beta release
96 31 rchan
      - Docker plugin (models) + sync
97 32 daviddavis
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
98
      - Content protection work (https://pulp.plan.io/issues/3968)
99
      - Katello P1 items (e.g. https://pulp.plan.io/issues/3802)
100 31 rchan
      - Installer wrap up
101 26 rchan
102
## Sprint 42
103 30 rchan
104 26 rchan
Dates: Friday Aug 24, 2018 - Thursday Sept 13, 2018  
105
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
106
Notes
107
108 27 rchan
  - Pulp 2 bugs/features:
109
      - 2.18.0 Module Errata support
110 26 rchan
      - bugs as prioritized by internal stakeholders
111
  - Pulp3 Core GA Features:
112 30 rchan
      - Lazy sync start this sprint (https://pulp.plan.io/issues/3693)
113 27 rchan
      - ~~RPM plugin (sync +~~ publish) 
114 26 rchan
      - Docker plugin (models)
115 28 daviddavis
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
116 26 rchan
      - ~~CLI progress~~ keep #3627 on sprint, this is blocked until bindings id/href is resolved- 
117 30 rchan
      - bindings id/href resolution - off-sprint prototype from @bizhang will unblock:
118
          - ~~3851, 3856, 3580,~~ 3836
119
      - Installer work - 1 FTE during this sprint  
120 26 rchan
        ~~\* Merge & complete docs tasks that have been partially complete for some time.~~
121 20 rchan
122
## Sprint 41
123
124
Dates: Friday Aug 3, 2018 - Thursday August 23, 2018  
125
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
126
Notes
127
128
  - Pulp 2 bugs/features:
129
      - Module Errata support
130
      - bugs as prioritized by Sat liasons
131 22 bizhang
  - Core GA Features:
132 24 rchan
      - CLI progress- keep #3627 on sprint, this is blocked until bindings id/href is resolved 
133
      - bindings id/href resolution - off-sprint prototype from @bizhang will unblock:
134 21 bmbouter
          - 3851, 3856, 3580, 3836
135
      - Installer work on sprint - 0.5 FTE starting on Aug 20th
136 20 rchan
      - Lazy sync start this sprint (https://pulp.plan.io/issues/3693)
137 21 bmbouter
      - Pulp 3 RPM (sync+publish) and Docker( models) Plugins on start again
138 20 rchan
      - Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
139 14 rchan
140
## Sprint 40
141
142
Dates: Friday July 13, 2018 - Thursday August 2, 2018  
143
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
144
Notes
145
146
  - Pulp 2 bugs/features:
147
      - Pulp 2.17 features:
148 18 milan
          - Rich Dependency Support
149 14 rchan
              - Weak dependencies? (see Issue #3847)
150
          - Advanced Modularity
151
          - Container/Docker plugin enhancements (3137)
152 15 rchan
  - Core GA Features:
153 19 bmbouter
      - CLI progress - feedback from July 2 deadline digested
154 14 rchan
      - Declarative Versions - waiting on input after deep dive, then https://pulp.plan.io/issues/3844
155 17 rchan
      - Installer work on sprint - no commitment from core team on staffing
156
      - Lazy sync still on hold. Let's focus on less & know this is ready to start.
157
      - Pulp 3 RPM and Docker Plugins on hold (again, focus on less & get done before start this again)
158 14 rchan
      - Performance bugs if staffing available - some of this is already in progress
159 12 rchan
160
## Sprint 39
161
162
Dates: Friday June 22, 2018 - Thursday July 12, 2018  
163
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
164
Notes
165
166
  - Pulp 2 bugs/features:
167
      - FIPS - can we aim to close all known stories that aren't blocked?
168
      - Pulp 2.17 features:
169
          - Advanced Modularity + Rich Dependency Support
170
          - Container/Docker plugin enhancements
171
  - Core GA Features:
172
      - Installer work on sprint - no commitment from core team on staffing
173 13 rchan
      - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
174
      - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested
175 12 rchan
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution
176 8 rchan
177
## Sprint 38
178
179
Dates: Friday June 1, 2018 - Thursday June 21, 2018  
180
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
181
Notes
182
183 9 rchan
  - Pulp 2 bugs/features:
184
      - FIPS
185 10 rchan
      - Modularity
186 1 rchan
      - Container/Docker plugin enhancements
187 10 rchan
  - Core GA Features:
188
      - Installerwork on sprint - no commitment from core team on staffing
189 11 rchan
  - Pause progress on Pulp 3 RPM and Docker Plugins
190
      - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint
191 8 rchan
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well
192 7 rchan
193
## Sprint 37
194
195
Dates: Friday May 11, 2018- Thursday May 31,2018  
196
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
197 1 rchan
Notes
198
199
  - Reserve time for fixing issues found after Core Beta released
200 10 rchan
  - Planning for conferences and Pulp 3.0 GA planning
201
202
Completion
203
204 7 rchan
  - Lazy Sync planning completed
205 5 rchan
206
## Sprint 36
207
208
Dates: Friday April 20, 2018- Thursday May 10,2018  
209
Sprint Goals/Focus: Pulp 3 Core Beta  
210
Notes
211
212 6 rchan
  - Items focused on remaining Pulp 3.0 Core Beta deliverables
213
  - Reserve time for fixing issues found after Core Beta released
214 5 rchan
  - Planning for conferences and Pulp 3.0 GA planning
215
216
## Sprint 35
217
218
Dates: Friday March 30, 2018- Thursday April 19,2018  
219
Sprint Goals/Focus: Pulp 3 Core Beta  
220
Notes
221
222
  - Items focused on Pulp 3.0 Core Beta deliverables
223 3 rchan
224
## Sprint 34
225 4 rchan
226 1 rchan
Dates: Friday March 9, 2018- Thursday March 29,2018  
227
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze  
228
Notes
229
230
  - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. 
231 4 rchan
  - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
232 1 rchan
  - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.