Sprint Plans » History » Sprint/Milestone 40
rchan, 11/26/2018 08:22 PM
1 | 1 | rchan | # Sprint Plans |
---|---|---|---|
2 | |||
3 | 36 | rchan | ## Sprint 46 |
4 | 35 | rchan | |
5 | 36 | rchan | Dates: Wednesday Nov 29, 2018 - Wednesday 20-Dec-2018 |
6 | 40 | rchan | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC + Pulp 3 Docker beta |
7 | Notes |
||
8 | 1 | rchan | |
9 | 40 | rchan | - Pulp 2 bugs/features: |
10 | - bugs as prioritized by internal stakeholders |
||
11 | - Pulp 2.19.0: |
||
12 | - Module Errata Depsolving |
||
13 | - Pulp3 Core GA Features: |
||
14 | - Lazy sync completed (https://pulp.plan.io/issues/3693) |
||
15 | - Docker publish |
||
16 | - Single Content work |
||
17 | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
||
18 | - Content protection work |
||
19 | - Documentation work |
||
20 | - Katello P1 - migrations |
||
21 | 38 | rchan | |
22 | 36 | rchan | ## Sprint 45 |
23 | 1 | rchan | |
24 | 35 | rchan | Dates: Friday Nov 2, 2018 - Tuesday 28-Nov-2018 |
25 | 34 | rchan | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC |
26 | Notes |
||
27 | |||
28 | 1 | rchan | - Pulp 2 bugs/features: |
29 | 34 | rchan | - bugs as prioritized by internal stakeholders |
30 | 37 | rchan | - 2.18.0 Module Errata Applicability |
31 | - Module Errata Depsolving |
||
32 | 34 | rchan | - Pulp3 Core GA Features: |
33 | - Lazy sync continues (https://pulp.plan.io/issues/3693) |
||
34 | - RPM plugin beta release |
||
35 | 1 | rchan | - Docker sync + publish |
36 | 38 | rchan | - Single Content work |
37 | 1 | rchan | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
38 | 38 | rchan | - Content protection work |
39 | 39 | rchan | - Documentation work |
40 | 35 | rchan | |
41 | ## Sprint 44 |
||
42 | |||
43 | Dates: Friday Oct 5, 2018 - Thursday ~~Oct 26~~ 01-Nov, 2018 |
||
44 | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC |
||
45 | Notes |
||
46 | |||
47 | - Pulp 2 bugs/features: |
||
48 | - bugs as prioritized by internal stakeholders |
||
49 | - 2.19.0 Module Errata Applicability & Depsolving |
||
50 | - Pulp3 Core GA Features: |
||
51 | - Lazy sync continues (https://pulp.plan.io/issues/3693) |
||
52 | 1 | rchan | - RPM plugin beta release |
53 | 35 | rchan | - Docker sync + publish |
54 | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
||
55 | 38 | rchan | - Content protection work |
56 | 35 | rchan | - Katello P1 items (e.g.?) |
57 | 34 | rchan | Decided to extend sprint through week after on-sight planning meeting to prep for next Sprint. |
58 | 31 | rchan | |
59 | ## Sprint 43 |
||
60 | 1 | rchan | |
61 | 34 | rchan | Dates: Friday Sept 14, 2018 - Thursday Oct 4, 2018 |
62 | 1 | rchan | Sprint Goals/Focus: Pulp 2 + Pulp 3 RC |
63 | 31 | rchan | Notes |
64 | 34 | rchan | |
65 | - Pulp 2 bugs/features: |
||
66 | 31 | rchan | ~~\*\* 2.18.0 Module Errata support~~ |
67 | - bugs as prioritized by internal stakeholders |
||
68 | - 2.19.0 Module Errata Applicability & Depsolving |
||
69 | 32 | daviddavis | - Pulp3 Core GA Features: |
70 | - Lazy sync continues (https://pulp.plan.io/issues/3693) |
||
71 | 33 | ipanova@redhat.com | - RPM plugin beta release |
72 | 31 | rchan | - Docker plugin (models) + sync |
73 | 32 | daviddavis | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
74 | - Content protection work (https://pulp.plan.io/issues/3968) |
||
75 | - Katello P1 items (e.g. https://pulp.plan.io/issues/3802) |
||
76 | 31 | rchan | - Installer wrap up |
77 | 26 | rchan | |
78 | ## Sprint 42 |
||
79 | 30 | rchan | |
80 | 26 | rchan | Dates: Friday Aug 24, 2018 - Thursday Sept 13, 2018 |
81 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
82 | Notes |
||
83 | |||
84 | 27 | rchan | - Pulp 2 bugs/features: |
85 | - 2.18.0 Module Errata support |
||
86 | 26 | rchan | - bugs as prioritized by internal stakeholders |
87 | - Pulp3 Core GA Features: |
||
88 | 30 | rchan | - Lazy sync start this sprint (https://pulp.plan.io/issues/3693) |
89 | 27 | rchan | - ~~RPM plugin (sync +~~ publish) |
90 | 26 | rchan | - Docker plugin (models) |
91 | 28 | daviddavis | - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
92 | 26 | rchan | - ~~CLI progress~~ keep #3627 on sprint, this is blocked until bindings id/href is resolved- |
93 | 30 | rchan | - bindings id/href resolution - off-sprint prototype from @bizhang will unblock: |
94 | - ~~3851, 3856, 3580,~~ 3836 |
||
95 | - Installer work - 1 FTE during this sprint |
||
96 | 26 | rchan | ~~\* Merge & complete docs tasks that have been partially complete for some time.~~ |
97 | 20 | rchan | |
98 | ## Sprint 41 |
||
99 | |||
100 | Dates: Friday Aug 3, 2018 - Thursday August 23, 2018 |
||
101 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
102 | Notes |
||
103 | |||
104 | - Pulp 2 bugs/features: |
||
105 | - Module Errata support |
||
106 | - bugs as prioritized by Sat liasons |
||
107 | 22 | bizhang | - Core GA Features: |
108 | 24 | rchan | - CLI progress- keep #3627 on sprint, this is blocked until bindings id/href is resolved |
109 | - bindings id/href resolution - off-sprint prototype from @bizhang will unblock: |
||
110 | 21 | bmbouter | - 3851, 3856, 3580, 3836 |
111 | - Installer work on sprint - 0.5 FTE starting on Aug 20th |
||
112 | 20 | rchan | - Lazy sync start this sprint (https://pulp.plan.io/issues/3693) |
113 | 21 | bmbouter | - Pulp 3 RPM (sync+publish) and Docker( models) Plugins on start again |
114 | 20 | rchan | - Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770)) |
115 | 14 | rchan | |
116 | ## Sprint 40 |
||
117 | |||
118 | Dates: Friday July 13, 2018 - Thursday August 2, 2018 |
||
119 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
120 | Notes |
||
121 | |||
122 | - Pulp 2 bugs/features: |
||
123 | - Pulp 2.17 features: |
||
124 | 18 | milan | - Rich Dependency Support |
125 | 14 | rchan | - Weak dependencies? (see Issue #3847) |
126 | - Advanced Modularity |
||
127 | - Container/Docker plugin enhancements (3137) |
||
128 | 15 | rchan | - Core GA Features: |
129 | 19 | bmbouter | - CLI progress - feedback from July 2 deadline digested |
130 | 14 | rchan | - Declarative Versions - waiting on input after deep dive, then https://pulp.plan.io/issues/3844 |
131 | 17 | rchan | - Installer work on sprint - no commitment from core team on staffing |
132 | - Lazy sync still on hold. Let's focus on less & know this is ready to start. |
||
133 | - Pulp 3 RPM and Docker Plugins on hold (again, focus on less & get done before start this again) |
||
134 | 14 | rchan | - Performance bugs if staffing available - some of this is already in progress |
135 | 12 | rchan | |
136 | ## Sprint 39 |
||
137 | |||
138 | Dates: Friday June 22, 2018 - Thursday July 12, 2018 |
||
139 | Sprint Goals/Focus: Pulp 2 + Pulp 3 GA |
||
140 | Notes |
||
141 | |||
142 | - Pulp 2 bugs/features: |
||
143 | - FIPS - can we aim to close all known stories that aren't blocked? |
||
144 | - Pulp 2.17 features: |
||
145 | - Advanced Modularity + Rich Dependency Support |
||
146 | - Container/Docker plugin enhancements |
||
147 | - Core GA Features: |
||
148 | - Installer work on sprint - no commitment from core team on staffing |
||
149 | 13 | rchan | - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins |
150 | - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested |
||
151 | 12 | rchan | - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution |
152 | 8 | rchan | |
153 | ## Sprint 38 |
||
154 | |||
155 | Dates: Friday June 1, 2018 - Thursday June 21, 2018 |
||
156 | Sprint Goals/Focus: Pulp 3 GA + Pulp 2 |
||
157 | Notes |
||
158 | |||
159 | 9 | rchan | - Pulp 2 bugs/features: |
160 | - FIPS |
||
161 | 10 | rchan | - Modularity |
162 | 1 | rchan | - Container/Docker plugin enhancements |
163 | 10 | rchan | - Core GA Features: |
164 | - Installerwork on sprint - no commitment from core team on staffing |
||
165 | 11 | rchan | - Pause progress on Pulp 3 RPM and Docker Plugins |
166 | - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint |
||
167 | 8 | rchan | - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well |
168 | 7 | rchan | |
169 | ## Sprint 37 |
||
170 | |||
171 | Dates: Friday May 11, 2018- Thursday May 31,2018 |
||
172 | Sprint Goals/Focus: Pulp 3 GA + Pulp 2 |
||
173 | 1 | rchan | Notes |
174 | |||
175 | - Reserve time for fixing issues found after Core Beta released |
||
176 | 10 | rchan | - Planning for conferences and Pulp 3.0 GA planning |
177 | |||
178 | Completion |
||
179 | |||
180 | 7 | rchan | - Lazy Sync planning completed |
181 | 5 | rchan | |
182 | ## Sprint 36 |
||
183 | |||
184 | Dates: Friday April 20, 2018- Thursday May 10,2018 |
||
185 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
186 | Notes |
||
187 | |||
188 | 6 | rchan | - Items focused on remaining Pulp 3.0 Core Beta deliverables |
189 | - Reserve time for fixing issues found after Core Beta released |
||
190 | 5 | rchan | - Planning for conferences and Pulp 3.0 GA planning |
191 | |||
192 | ## Sprint 35 |
||
193 | |||
194 | Dates: Friday March 30, 2018- Thursday April 19,2018 |
||
195 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
196 | Notes |
||
197 | |||
198 | - Items focused on Pulp 3.0 Core Beta deliverables |
||
199 | 3 | rchan | |
200 | ## Sprint 34 |
||
201 | 4 | rchan | |
202 | 1 | rchan | Dates: Friday March 9, 2018- Thursday March 29,2018 |
203 | Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze |
||
204 | Notes |
||
205 | |||
206 | - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. |
||