Project

Profile

Help

Actions

Sprint Plans » History » Revision 25

« Previous | Revision 25/182 (diff) | Next »
bmbouter, 08/03/2018 10:43 PM
DeclarativeVersion was merged in Sprint 40


Sprint Plans

Sprint 41

Dates: Friday Aug 3, 2018 - Thursday August 23, 2018
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA
Notes

  • Pulp 2 bugs/features:
    • Module Errata support
    • bugs as prioritized by Sat liasons
  • Core GA Features:
    • CLI progress- keep #3627 on sprint, this is blocked until bindings id/href is resolved
    • bindings id/href resolution - off-sprint prototype from bizhang will unblock:
      • 3851, 3856, 3580, 3836
    • Installer work on sprint - 0.5 FTE starting on Aug 20th
    • Lazy sync start this sprint (https://pulp.plan.io/issues/3693)
    • Pulp 3 RPM (sync+publish) and Docker( models) Plugins on start again
    • Performance bugs (1 performance issue and 1 benchmark comparison issue)

Sprint 40

Dates: Friday July 13, 2018 - Thursday August 2, 2018
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA
Notes

  • Pulp 2 bugs/features:
    • Pulp 2.17 features:
      • Rich Dependency Support
        • Weak dependencies? (see Issue #3847)
      • Advanced Modularity
      • Container/Docker plugin enhancements (3137)
  • Core GA Features:
    • CLI progress - feedback from July 2 deadline digested
    • Declarative Versions - waiting on input after deep dive, then https://pulp.plan.io/issues/3844
    • Installer work on sprint - no commitment from core team on staffing
    • Lazy sync still on hold. Let's focus on less & know this is ready to start.
    • Pulp 3 RPM and Docker Plugins on hold (again, focus on less & get done before start this again)
    • Performance bugs if staffing available - some of this is already in progress

Sprint 39

Dates: Friday June 22, 2018 - Thursday July 12, 2018
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA
Notes

  • Pulp 2 bugs/features:
    • FIPS - can we aim to close all known stories that aren't blocked?
    • Pulp 2.17 features:
      • Advanced Modularity + Rich Dependency Support
      • Container/Docker plugin enhancements
  • Core GA Features:
    • Installer work on sprint - no commitment from core team on staffing
    • Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
    • CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested
  • Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution

Sprint 38

Dates: Friday June 1, 2018 - Thursday June 21, 2018
Sprint Goals/Focus: Pulp 3 GA + Pulp 2
Notes

  • Pulp 2 bugs/features:
    • FIPS
    • Modularity
    • Container/Docker plugin enhancements
  • Core GA Features:
    • Installerwork on sprint - no commitment from core team on staffing
  • Pause progress on Pulp 3 RPM and Docker Plugins
    • Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint
  • Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well

Sprint 37

Dates: Friday May 11, 2018- Thursday May 31,2018
Sprint Goals/Focus: Pulp 3 GA + Pulp 2
Notes

  • Reserve time for fixing issues found after Core Beta released
  • Planning for conferences and Pulp 3.0 GA planning

Completion

  • Lazy Sync planning completed

Sprint 36

Dates: Friday April 20, 2018- Thursday May 10,2018
Sprint Goals/Focus: Pulp 3 Core Beta
Notes

  • Items focused on remaining Pulp 3.0 Core Beta deliverables
  • Reserve time for fixing issues found after Core Beta released
  • Planning for conferences and Pulp 3.0 GA planning

Sprint 35

Dates: Friday March 30, 2018- Thursday April 19,2018
Sprint Goals/Focus: Pulp 3 Core Beta
Notes

  • Items focused on Pulp 3.0 Core Beta deliverables

Sprint 34

Dates: Friday March 9, 2018- Thursday March 29,2018
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze
Notes

  • Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint.
  • Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
  • Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.

Updated by bmbouter over 6 years ago · 25 revisions