# Sprint Plans
2
3 14 rchan
## Sprint 40
4
5
Dates: Friday July 13, 2018 - Thursday August 2, 2018  
6
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
7
Notes
8
9
  - Pulp 2 bugs/features:
10
      - Pulp 2.17 features:
11
          - Rich Dependency Support
12
          - Advanced Modularity
13
          - Container/Docker plugin enhancements (3137)
14
  - Core GA Features:
15
      - CLI progress - feedback from July 2 deadline digested
16 15 rchan
      - Lazy sync start
17
      - Pending Versions - \<what progress can we make here\>
18 14 rchan
      - Installer work on sprint - no commitment from core team on staffing
19 16 rchan
      - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins  
20
        \<please make comments here\>  
21
        performance bugs
22 14 rchan
23 12 rchan
## Sprint 39
24
25
Dates: Friday June 22, 2018 - Thursday July 12, 2018  
26
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
27
Notes
28
29
  - Pulp 2 bugs/features:
30
      - FIPS - can we aim to close all known stories that aren't blocked?
31
      - Pulp 2.17 features:
32
          - Advanced Modularity + Rich Dependency Support
33
          - Container/Docker plugin enhancements
34
  - Core GA Features:
35
      - Installer work on sprint - no commitment from core team on staffing
36
      - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
37 13 rchan
      - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested
38
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution
39 12 rchan
40 8 rchan
## Sprint 38
41
42
Dates: Friday June 1, 2018 - Thursday June 21, 2018  
43
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
44
Notes
45
46
  - Pulp 2 bugs/features:
47 9 rchan
      - FIPS
48
      - Modularity
49 10 rchan
      - Container/Docker plugin enhancements
50 1 rchan
  - Core GA Features:
51 10 rchan
      - Installerwork on sprint - no commitment from core team on staffing
52
  - Pause progress on Pulp 3 RPM and Docker Plugins
53 11 rchan
      - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint
54
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well
55 8 rchan
56 7 rchan
## Sprint 37
57
58
Dates: Friday May 11, 2018- Thursday May 31,2018  
59
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
60
Notes
61 1 rchan
62
  - Reserve time for fixing issues found after Core Beta released
63
  - Planning for conferences and Pulp 3.0 GA planning
64 10 rchan
65
Completion
66
67
  - Lazy Sync planning completed
68 7 rchan
69 5 rchan
## Sprint 36
70
71
Dates: Friday April 20, 2018- Thursday May 10,2018  
72
Sprint Goals/Focus: Pulp 3 Core Beta  
73
Notes
74
75
  - Items focused on remaining Pulp 3.0 Core Beta deliverables
76 6 rchan
  - Reserve time for fixing issues found after Core Beta released
77
  - Planning for conferences and Pulp 3.0 GA planning
78 5 rchan
79
## Sprint 35
80
81
Dates: Friday March 30, 2018- Thursday April 19,2018  
82
Sprint Goals/Focus: Pulp 3 Core Beta  
83
Notes
84
85
  - Items focused on Pulp 3.0 Core Beta deliverables
86
87 3 rchan
## Sprint 34
88
89 4 rchan
Dates: Friday March 9, 2018- Thursday March 29,2018  
90 1 rchan
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze  
91
Notes
92
93
  - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. 
94
  - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
95 4 rchan
  - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.