Sprint Plans » History » Sprint/Milestone 14

rchan, 07/06/2018 09:49 PM

1 1 rchan
# Sprint Plans
2
3 14 rchan
## Sprint 40
4
5
Dates: Friday July 13, 2018 - Thursday August 2, 2018  
6
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
7
Notes
8
9
  - Pulp 2 bugs/features:
10
      - Pulp 2.17 features:
11
          - Rich Dependency Support
12
          - Advanced Modularity
13
          - Container/Docker plugin enhancements (3137)
14
  - Core GA Features:
15
      - CLI progress - feedback from July 2 deadline digested
16
      - Lazy sync bootstrap
17
      - Pending Versions
18
      - Installer work on sprint - no commitment from core team on staffing
19
      - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
20
21 12 rchan
## Sprint 39
22
23
Dates: Friday June 22, 2018 - Thursday July 12, 2018  
24
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
25
Notes
26
27
  - Pulp 2 bugs/features:
28
      - FIPS - can we aim to close all known stories that aren't blocked?
29
      - Pulp 2.17 features:
30
          - Advanced Modularity + Rich Dependency Support
31
          - Container/Docker plugin enhancements
32
  - Core GA Features:
33
      - Installer work on sprint - no commitment from core team on staffing
34
      - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
35 13 rchan
      - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested
36
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution
37 12 rchan
38 8 rchan
## Sprint 38
39
40
Dates: Friday June 1, 2018 - Thursday June 21, 2018  
41
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
42
Notes
43
44
  - Pulp 2 bugs/features:
45 9 rchan
      - FIPS
46
      - Modularity
47 10 rchan
      - Container/Docker plugin enhancements
48 1 rchan
  - Core GA Features:
49 10 rchan
      - Installerwork on sprint - no commitment from core team on staffing
50
  - Pause progress on Pulp 3 RPM and Docker Plugins
51 11 rchan
      - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint
52
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well
53 8 rchan
54 7 rchan
## Sprint 37
55
56
Dates: Friday May 11, 2018- Thursday May 31,2018  
57
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
58
Notes
59 1 rchan
60
  - Reserve time for fixing issues found after Core Beta released
61
  - Planning for conferences and Pulp 3.0 GA planning
62 10 rchan
63
Completion
64
65
  - Lazy Sync planning completed
66 7 rchan
67 5 rchan
## Sprint 36
68
69
Dates: Friday April 20, 2018- Thursday May 10,2018  
70
Sprint Goals/Focus: Pulp 3 Core Beta  
71
Notes
72
73
  - Items focused on remaining Pulp 3.0 Core Beta deliverables
74 6 rchan
  - Reserve time for fixing issues found after Core Beta released
75
  - Planning for conferences and Pulp 3.0 GA planning
76 5 rchan
77
## Sprint 35
78
79
Dates: Friday March 30, 2018- Thursday April 19,2018  
80
Sprint Goals/Focus: Pulp 3 Core Beta  
81
Notes
82
83
  - Items focused on Pulp 3.0 Core Beta deliverables
84
85 3 rchan
## Sprint 34
86
87 4 rchan
Dates: Friday March 9, 2018- Thursday March 29,2018  
88 1 rchan
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze  
89
Notes
90
91
  - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. 
92
  - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
93 4 rchan
  - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.