Sprint Plans » History » Sprint/Milestone 11
rchan, 06/01/2018 04:26 PM
1 | 1 | rchan | # Sprint Plans |
---|---|---|---|
2 | |||
3 | 8 | rchan | ## Sprint 38 |
4 | |||
5 | Dates: Friday June 1, 2018 - Thursday June 21, 2018 |
||
6 | Sprint Goals/Focus: Pulp 3 GA + Pulp 2 |
||
7 | Notes |
||
8 | |||
9 | - Pulp 2 bugs/features: |
||
10 | 9 | rchan | - FIPS |
11 | - Modularity |
||
12 | 10 | rchan | - Container/Docker plugin enhancements |
13 | 1 | rchan | - Core GA Features: |
14 | 10 | rchan | - Installerwork on sprint - no commitment from core team on staffing |
15 | - Pause progress on Pulp 3 RPM and Docker Plugins |
||
16 | 11 | rchan | - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint |
17 | - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well |
||
18 | 8 | rchan | |
19 | 7 | rchan | ## Sprint 37 |
20 | |||
21 | Dates: Friday May 11, 2018- Thursday May 31,2018 |
||
22 | Sprint Goals/Focus: Pulp 3 GA + Pulp 2 |
||
23 | Notes |
||
24 | 1 | rchan | |
25 | - Reserve time for fixing issues found after Core Beta released |
||
26 | - Planning for conferences and Pulp 3.0 GA planning |
||
27 | 10 | rchan | |
28 | Completion |
||
29 | |||
30 | - Lazy Sync planning completed |
||
31 | 7 | rchan | |
32 | 5 | rchan | ## Sprint 36 |
33 | |||
34 | Dates: Friday April 20, 2018- Thursday May 10,2018 |
||
35 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
36 | Notes |
||
37 | |||
38 | - Items focused on remaining Pulp 3.0 Core Beta deliverables |
||
39 | 6 | rchan | - Reserve time for fixing issues found after Core Beta released |
40 | - Planning for conferences and Pulp 3.0 GA planning |
||
41 | 5 | rchan | |
42 | ## Sprint 35 |
||
43 | |||
44 | Dates: Friday March 30, 2018- Thursday April 19,2018 |
||
45 | Sprint Goals/Focus: Pulp 3 Core Beta |
||
46 | Notes |
||
47 | |||
48 | - Items focused on Pulp 3.0 Core Beta deliverables |
||
49 | |||
50 | 3 | rchan | ## Sprint 34 |
51 | |||
52 | 4 | rchan | Dates: Friday March 9, 2018- Thursday March 29,2018 |
53 | 1 | rchan | Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze |
54 | Notes |
||
55 | |||
56 | - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. |
||
57 | - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag" |
||
58 | 4 | rchan | - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18. |