# Pulp 2.9 Release Schedule 

 |              |                           |                                               | 
 | ---------- | ----------------------- | ------------------------------------------- | 
 | 2016-05-17 | 2.9 branches created      | Build system adapted to build from branches | 
 | 2016-06-07 | 2.9.0 Feature freeze      | Only bug fixes after this                     | 
 | 2016-06-14 | 2.9.0 Beta                |                                               | 
 | 2016-06-21 | 2.9.0 Release candidate | Final Freeze                                  | 
 | 2016-06-28 | 2.9.0 Release             |                                               | 

 # Pulp 2.10 Release Schedule Definitions 

 |              |                     | 
 | ---------- | ----------------- | 
 | 2016-06-28 | Branches created    | 
 | 2016-07-19 | Feature freeze      | 
 | 2016-07-26 | Beta                | 
 | 2016-08-02 | Release candidate | 
 | 2016-08-09 | GA Release          | 

 # Definitions 

 **Beta** - All bug fixes that need to be in the release are complete. Dev believes the release is ready.   
 **Feature Freeze** Release candidate - No new features allowed after this date. Though exceptions can be made for work waiting on review, the submitter should attempt to have work reviewed and merged before the freeze date.   
 **Release candidate** - QE has performed their testing and is satisfied to release. No new bug fixes after this point. Regressions or other urgent bug fixes will be handled case by case. 

 # Release Cadence 

 The release cycle will begin on the day of the previous GA release. 

   - 0 weeks: New branch created, build system adapted to build from branches 
   - 3 weeks: Feature freeze 
   - 4 weeks: Beta release 
   - 5 weeks: Release Candidate 