Release Schedule » History » Revision 8

« Previous | Revision 8/86 (diff) | Next »
amacdona@redhat.com, 06/06/2016 05:16 PM


Pulp 2.9 Release Schedule

2016-05-17 2.9 branches created Build system adapted to build from branches
2016-06-07 2.9.0 Feature freeze Only bug fixes after this
2016-06-14 2.9.0 Beta
2016-06-21 2.9.0 Release candidate Final Freeze
2016-06-28 2.9.0 Release

Pulp 2.10 Release Schedule

2016-06-28 Branches created
2016-07-19 Feature freeze
2016-07-26 Beta
2016-08-02 Release candidate
2016-08-09 GA Release

Definitions

Beta - All bug fixes that need to be in the release are complete. Dev believes the release is ready.
Feature Freeze - No new features allowed after this date. Though exceptions can be made for work waiting on review, the submitter should attempt to have work reviewed and merged before the freeze date.
Release candidate - QE has performed their testing and is satisfied to release. No new bug fixes after this point. Regressions or other urgent bug fixes will be handled case by case.

Release Cadence

The release cycle will begin on the day of the previous GA release.

  • 0 weeks: New branch created, build system adapted to build from branches
  • 3 weeks: Feature freeze
  • 4 weeks: Beta release
  • 5 weeks: Release Candidate
  • 6 weeks: GA Release

Updated by amacdona@redhat.com over 8 years ago · 8 revisions