1 7 mhrivnak
# Pulp 2.9 Release Schedule
2 1 rbarlow
3 3 rbarlow
|            |                         |                                             |
4
| ---------- | ----------------------- | ------------------------------------------- |
5
| 2016-05-17 | 2.9 branches created    | Build system adapted to build from branches |
6 6 bmbouter
| 2016-06-07 | 2.9.0 Feature freeze    | Only bug fixes after this                   |
7 3 rbarlow
| 2016-06-14 | 2.9.0 Beta              |                                             |
8
| 2016-06-21 | 2.9.0 Release candidate | Final Freeze                                |
9
| 2016-06-28 | 2.9.0 Release           |                                             |
10 1 rbarlow
11 8 amacdona@redhat.com
# Pulp 2.10 Release Schedule
12
13
|            |                   |
14
| ---------- | ----------------- |
15
| 2016-06-28 | Branches created  |
16
| 2016-07-19 | Feature freeze    |
17
| 2016-07-26 | Beta              |
18
| 2016-08-02 | Release candidate |
19
| 2016-08-09 | GA Release        |
20
21 1 rbarlow
# Definitions
22
23 8 amacdona@redhat.com
**Beta** - All bug fixes that need to be in the release are complete. Dev believes the release is ready.  
24
**Feature Freeze** - No new features allowed after this date. Though exceptions can be made for work waiting on review, the submitter should attempt to have work reviewed and merged before the freeze date.  
25
**Release candidate** - QE has performed their testing and is satisfied to release. No new bug fixes after this point. Regressions or other urgent bug fixes will be handled case by case.
26
27 9 amacdona@redhat.com
# Y Release Cadence
28 8 amacdona@redhat.com
29
The release cycle will begin on the day of the previous GA release.
30
31 11 amacdona@redhat.com
  - week 0: (X -1) GA Release, new branch created, build system adapted to build from branches
32
  - week 3: Feature freeze
33
  - week 4: Beta release
34
  - week 5: Release Candidate
35
  - week 6: GA Release
36 9 amacdona@redhat.com
37
# Z Release Cadence
38
39 11 amacdona@redhat.com
  - week 0: (Z-1) GA Release
40
  - week 1: Beta Release
41
  - week 2: GA Release