320 Crane Release Status » History » Sprint/Milestone 4
ipanova@redhat.com, 05/04/2018 06:17 PM
1 | 3 | ipanova@redhat.com | # Crane 3.2.0 Release Status |
---|---|---|---|
2 | 2 | ipanova@redhat.com | |
3 | 3 | ipanova@redhat.com | The current tentative release date for 3.2.0 is May 30, 2018 |
4 | 2 | ipanova@redhat.com | |
5 | ## Checklist |
||
6 | |||
7 | The first item on the list **not** struck through is in progress. |
||
8 | |||
9 | - Dev Freeze date |
||
10 | - -May 9, 2018 |
||
11 | - Beta Build date. |
||
12 | - -May 16, 2018 |
||
13 | - Prerequisites to building: |
||
14 | - -Issues blocking release |
||
15 | - -No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar) |
||
16 | - -master branch now tracks development for next Y release |
||
17 | - -build system adapted to build from new dev branch |
||
18 | - -test scratch build from beta branch |
||
19 | - -beta is built from release branch |
||
20 | 4 | ipanova@redhat.com | - waiting period (1 week after beta release date) before GA |
21 | - -GA Date: May 23, 2018 |
||
22 | 3 | ipanova@redhat.com | - verify [issues with](https://pulp.plan.io/issues?utf8=%E2%9C%93&set_filter=1&f%5B%5D=cf_36&op%5Bcf_36%5D=%3D&v%5Bcf_36%5D%5B%5D=1&f%5B%5D=cf_13&op%5Bcf_13%5D=%3D&v%5Bcf_13%5D%5B%5D=3.2.0&f%5B%5D=&c%5B%5D=project&c%5B%5D=tracker&c%5B%5D=status&c%5B%5D=priority&c%5B%5D=cf_5&c%5B%5D=subject&c%5B%5D=author&c%5B%5D=assigned_to&c%5B%5D=cf_3&c%5B%5D=cf_4&group_by=project&t%5B%5D=) "verification required" set |
23 | 2 | ipanova@redhat.com | |
24 | 3 | ipanova@redhat.com | The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 3.2.0 release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details. |
25 | 2 | ipanova@redhat.com | |
26 | If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available May 30, 2018. This page will be updated as progress is made. |