2.17.0 Release Status¶
The current tentative release date for 2.17.0 is May 30, 2018
Checklist¶
The first item on the list not struck through is in progress.
- Dev Freeze date
- -May 9, 2018
- Beta Build date.
- -May 16, 2018
- Prerequisites to building:
- -Issues blocking release
- -No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar)
- -master branch now tracks development for next Y release
- -build system adapted to build from new dev branch
- -test scratch build from beta branch
- -beta is built from release branch
- waiting period (1 week after beta release date) before RC
- -RC Date: May 23, 2018
- waiting period (1 week after RC release date) before GA
- -GA Date: May 30, 2018
- verify issues with "verification required" set
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 2.17.0 release progresses. See the Release Schedule for more details.
If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available May 30, 2018. This page will be updated as progress is made.