# Crane 3.2.0 Release Status
2 2 ipanova@redhat.com
3 3 ipanova@redhat.com
The current tentative release date for 3.2.0 is May 30, 2018
4 2 ipanova@redhat.com
5
## Checklist
6
7
The first item on the list **not** struck through is in progress.
8
9
  - Dev Freeze date 
10
      - -May 9, 2018
11
  - Beta Build date.
12
      - -May 16, 2018
13
  - Prerequisites to building:
14
      - -Issues blocking release
15
      - -No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar)
16
  - -master branch now tracks development for next Y release
17
  - -build system adapted to build from new dev branch
18
  - -test scratch build from beta branch
19
  - -beta is built from release branch
20
  - waiting period (1 week after beta release date) before RC
21
      - -RC Date: May 23, 2018
22
  - waiting period (1 week after RC release date) before GA
23
      - -GA Date: May 30, 2018
24 3 ipanova@redhat.com
  - verify [issues with](https://pulp.plan.io/issues?utf8=%E2%9C%93&set_filter=1&f%5B%5D=cf_36&op%5Bcf_36%5D=%3D&v%5Bcf_36%5D%5B%5D=1&f%5B%5D=cf_13&op%5Bcf_13%5D=%3D&v%5Bcf_13%5D%5B%5D=3.2.0&f%5B%5D=&c%5B%5D=project&c%5B%5D=tracker&c%5B%5D=status&c%5B%5D=priority&c%5B%5D=cf_5&c%5B%5D=subject&c%5B%5D=author&c%5B%5D=assigned_to&c%5B%5D=cf_3&c%5B%5D=cf_4&group_by=project&t%5B%5D=) "verification required" set
25 2 ipanova@redhat.com
26 3 ipanova@redhat.com
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 3.2.0 release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.
27 2 ipanova@redhat.com
28
If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available May 30, 2018. This page will be updated as progress is made.