Project

Profile

Help

2190 Release Schedule » History » Sprint/Milestone 7

rchan, 03/08/2019 08:24 PM

1 1 rchan
# 2.19.0 Release Schedule
2
3 5 rchan
***This is an early draft for planning purposes. Not ready to socialize yet, but helpful for us to start discussing options.***
4 1 rchan
5 7 rchan
The current tentative release date for 2.19.0 is April 2, 2019
6 4 rchan
7 1 rchan
## Checklist
8
9
The first item on the list **not** struck through is in progress.
10
11
  - Dev Freeze date 
12 6 rchan
      - March 12, 2019
13 1 rchan
  - Beta Build date.
14 6 rchan
      - March 19, 2019
15 1 rchan
      - - Targeting all content here: https://pulp.plan.io/versions/\<?\>
16
  - Prerequisites to building:
17
      - Issues blocking release
18
      - No procedural issues blocking this release (broken CI env, and similar)
19
  - waiting period (1 week after beta release date) before RC
20 6 rchan
      - RC Date: March 26, 2019
21 1 rchan
  - waiting period (1 week after RC release date) before GA
22 6 rchan
      - GA Date: April 2, 2019
23 1 rchan
  - verify [issues with](https://pulp.plan.io/issues?utf8=%E2%9C%93&set_filter=1&f%5B%5D=cf_4&op%5Bcf_4%5D=%3D&v%5Bcf_4%5D%5B%5D=2.19.0&f%5B%5D=cf_36&op%5Bcf_36%5D=%3D&v%5Bcf_36%5D%5B%5D=1&f%5B%5D=&c%5B%5D=project&c%5B%5D=tracker&c%5B%5D=status&c%5B%5D=priority&c%5B%5D=cf_5&c%5B%5D=subject&c%5B%5D=author&c%5B%5D=assigned_to&c%5B%5D=cf_3&c%5B%5D=cf_4&group_by=project&t%5B%5D=) "verification required" set
24
25 3 rchan
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 2.19.0 release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.
26 1 rchan
27 6 rchan
If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available April 2, 2019. This page will be updated as progress is made.
28 1 rchan
29
Release Contact: tbd on freenode (#pulp and#pulp-dev)