# 2.17.0 Release Schedule
2
3
The current tentative release date for 2.17.0 is August 20, 2018
4
5
## Checklist
6
7
The first item on the list **not** struck through is in progress.
8
9
  - Dev Freeze date 
10 3 rchan
      - <span style="color:red;">RED - We have late breaking requirements targetting added to query on next line by 7/27. Most likely move this date back. Stay tuned</span>
11 1 ipanova@redhat.com
      - -July 30, 2018
12 2 rchan
      - - Targeting all content here: https://pulp.plan.io/versions/63
13 1 ipanova@redhat.com
  - Beta Build date.
14
      - -August 6, 2018
15
  - Prerequisites to building:
16
      - -Issues blocking release
17
      - -No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar)
18
  - -master branch now tracks development for next Y release
19
  - -build system adapted to build from new dev branch
20
  - -test scratch build from beta branch
21
  - -beta is built from release branch
22
  - waiting period (1 week after beta release date) before RC
23
      - -RC Date: August 13, 2018
24
  - waiting period (1 week after RC release date) before GA
25
      - -GA Date: August 20, 2018
26
  - verify [issues with](https://pulp.plan.io/issues?utf8=%E2%9C%93&set_filter=1&f%5B%5D=cf_4&op%5Bcf_4%5D=%3D&v%5Bcf_4%5D%5B%5D=2.17.0&f%5B%5D=cf_36&op%5Bcf_36%5D=%3D&v%5Bcf_36%5D%5B%5D=1&f%5B%5D=&c%5B%5D=project&c%5B%5D=tracker&c%5B%5D=status&c%5B%5D=priority&c%5B%5D=cf_5&c%5B%5D=subject&c%5B%5D=author&c%5B%5D=assigned_to&c%5B%5D=cf_3&c%5B%5D=cf_4&group_by=project&t%5B%5D=) "verification required" set
27
28
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 2.17.0 release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.
29
30
If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available August 20, 2018. This page will be updated as progress is made.
31 4 rchan
32
Release Contact: asmacdo on freenode (#pulp and#pulp-dev)