Project

Profile

Help

2131 Release Status » History » Sprint/Milestone 3

bizhang, 05/16/2017 02:43 PM

1 1 bizhang
# 2.13.1 Release Status
2
3
This release is currently **scheduled**.
4
5
"Issues Addressed": http://bit.ly/2pPKNCC
6
7
## Checklist
8
9
The first item on the list **not** struck through is in progress.
10
11 2 bizhang
  - Beta Build date
12 1 bizhang
      - May 16, 2017
13
  - Prerequisites to building:
14 3 bizhang
      - ~~No open issues blocking this release~~
15
      - ~~Issues with the "verification required" field set verified.~~
16
      - ~~No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar)~~
17 1 bizhang
  - test scratch build from beta branch
18
      - Automated test results approved by QE
19
  - waiting period (1 week after beta 1 release date) before GA is allowed
20
  - beta release promoted to GA May 23, 2017 at the earliest
21
22
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.