## Sprint 42
4
5
Dates: Friday Aug 24, 2018 - Thursday Sept 14, 2018  
6
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
7
Notes
8
9
  - Pulp 2 bugs/features:
10 27 rchan
      - 2.18.0 Module Errata support
11
      - bugs as prioritized by internal stakeholders
12 26 rchan
  - Pulp3 Core GA Features:
13
      - Lazy sync start this sprint (https://pulp.plan.io/issues/3693)
14 27 rchan
      - RPM plugin (sync+publish) 
15
      - Docker plugin (models)
16 26 rchan
      - Continue Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
17 28 daviddavis
      - ~~CLI progress~~ keep #3627 on sprint, this is blocked until bindings id/href is resolved- 
18 26 rchan
      - bindings id/href resolution - off-sprint prototype from @bizhang will unblock:
19
          - 3851, 3856, 3580, 3836
20
      - Installer work - 0.5 FTE starting on Aug 20th
21
22 20 rchan
## Sprint 41
23
24
Dates: Friday Aug 3, 2018 - Thursday August 23, 2018  
25
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
26
Notes
27
28
  - Pulp 2 bugs/features:
29
      - Module Errata support
30
      - bugs as prioritized by Sat liasons
31
  - Core GA Features:
32 22 bizhang
      - CLI progress- keep #3627 on sprint, this is blocked until bindings id/href is resolved 
33 24 rchan
      - bindings id/href resolution - off-sprint prototype from @bizhang will unblock:
34
          - 3851, 3856, 3580, 3836
35 21 bmbouter
      - Installer work on sprint - 0.5 FTE starting on Aug 20th
36
      - Lazy sync start this sprint (https://pulp.plan.io/issues/3693)
37 20 rchan
      - Pulp 3 RPM (sync+publish) and Docker( models) Plugins on start again
38 21 bmbouter
      - Performance bugs (1 [performance issue](https://pulp.plan.io/issues/3812) and 1 [benchmark comparison issue](https://pulp.plan.io/issues/3770))
39 20 rchan
40 14 rchan
## Sprint 40
41
42
Dates: Friday July 13, 2018 - Thursday August 2, 2018  
43
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
44
Notes
45
46
  - Pulp 2 bugs/features:
47
      - Pulp 2.17 features:
48
          - Rich Dependency Support
49 18 milan
              - Weak dependencies? (see Issue #3847)
50 14 rchan
          - Advanced Modularity
51
          - Container/Docker plugin enhancements (3137)
52
  - Core GA Features:
53 15 rchan
      - CLI progress - feedback from July 2 deadline digested
54 19 bmbouter
      - Declarative Versions - waiting on input after deep dive, then https://pulp.plan.io/issues/3844
55 14 rchan
      - Installer work on sprint - no commitment from core team on staffing
56 17 rchan
      - Lazy sync still on hold. Let's focus on less & know this is ready to start.
57
      - Pulp 3 RPM and Docker Plugins on hold (again, focus on less & get done before start this again)
58
      - Performance bugs if staffing available - some of this is already in progress
59 14 rchan
60 12 rchan
## Sprint 39
61
62
Dates: Friday June 22, 2018 - Thursday July 12, 2018  
63
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA  
64
Notes
65
66
  - Pulp 2 bugs/features:
67
      - FIPS - can we aim to close all known stories that aren't blocked?
68
      - Pulp 2.17 features:
69
          - Advanced Modularity + Rich Dependency Support
70
          - Container/Docker plugin enhancements
71
  - Core GA Features:
72
      - Installer work on sprint - no commitment from core team on staffing
73
      - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
74 13 rchan
      - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested
75
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution
76 12 rchan
77 8 rchan
## Sprint 38
78
79
Dates: Friday June 1, 2018 - Thursday June 21, 2018  
80
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
81
Notes
82
83
  - Pulp 2 bugs/features:
84 9 rchan
      - FIPS
85
      - Modularity
86 10 rchan
      - Container/Docker plugin enhancements
87 1 rchan
  - Core GA Features:
88 10 rchan
      - Installerwork on sprint - no commitment from core team on staffing
89
  - Pause progress on Pulp 3 RPM and Docker Plugins
90 11 rchan
      - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint
91
  - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well
92 8 rchan
93 7 rchan
## Sprint 37
94
95
Dates: Friday May 11, 2018- Thursday May 31,2018  
96
Sprint Goals/Focus: Pulp 3 GA + Pulp 2  
97
Notes
98 1 rchan
99
  - Reserve time for fixing issues found after Core Beta released
100
  - Planning for conferences and Pulp 3.0 GA planning
101 10 rchan
102
Completion
103
104
  - Lazy Sync planning completed
105 7 rchan
106 5 rchan
## Sprint 36
107
108
Dates: Friday April 20, 2018- Thursday May 10,2018  
109
Sprint Goals/Focus: Pulp 3 Core Beta  
110
Notes
111
112
  - Items focused on remaining Pulp 3.0 Core Beta deliverables
113 6 rchan
  - Reserve time for fixing issues found after Core Beta released
114
  - Planning for conferences and Pulp 3.0 GA planning
115 5 rchan
116
## Sprint 35
117
118
Dates: Friday March 30, 2018- Thursday April 19,2018  
119
Sprint Goals/Focus: Pulp 3 Core Beta  
120
Notes
121
122
  - Items focused on Pulp 3.0 Core Beta deliverables
123
124 3 rchan
## Sprint 34
125
126 4 rchan
Dates: Friday March 9, 2018- Thursday March 29,2018  
127 1 rchan
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze  
128
Notes
129
130
  - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint. 
131
  - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
132 4 rchan
  - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.