Project

Profile

Help

Sprint Plans » History » Revision 17

Revision 16 (rchan, 07/06/2018 10:02 PM) → Revision 17/182 (rchan, 07/10/2018 09:19 PM)

# Sprint Plans 

 ## Sprint 40 

 Dates: Friday July 13, 2018 - Thursday August 2, 2018   
 Sprint Goals/Focus: Pulp 2 + Pulp 3 GA   
 Notes 

   - Pulp 2 bugs/features: 
       - Pulp 2.17 features: 
           - Rich Dependency Support 
               - Weak dependencies? 
           - Advanced Modularity 
           - Container/Docker plugin enhancements (3137) 
   - Core GA Features: 
       - CLI progress - feedback from July 2 deadline digested 
       - Declarative Lazy sync start 
       - Pending Versions - \<what progress can we make here\> 
       - Installer work on sprint - no commitment from core team on staffing 
       - Lazy sync still Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on hold. Let's focus on less & know this is ready to start. 
       - Pulp 3 RPM and Docker Plugins on hold (again, focus on less & get done before start this again) 
       - Performance   
         \<please make comments here\>   
         performance bugs if staffing available - some of this is already in progress 

 ## Sprint 39 

 Dates: Friday June 22, 2018 - Thursday July 12, 2018   
 Sprint Goals/Focus: Pulp 2 + Pulp 3 GA   
 Notes 

   - Pulp 2 bugs/features: 
       - FIPS - can we aim to close all known stories that aren't blocked? 
       - Pulp 2.17 features: 
           - Advanced Modularity + Rich Dependency Support 
           - Container/Docker plugin enhancements 
   - Core GA Features: 
       - Installer work on sprint - no commitment from core team on staffing 
       - Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins 
       - CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested 
   - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution 

 ## Sprint 38 

 Dates: Friday June 1, 2018 - Thursday June 21, 2018   
 Sprint Goals/Focus: Pulp 3 GA + Pulp 2   
 Notes 

   - Pulp 2 bugs/features: 
       - FIPS 
       - Modularity 
       - Container/Docker plugin enhancements 
   - Core GA Features: 
       - Installerwork on sprint - no commitment from core team on staffing 
   - Pause progress on Pulp 3 RPM and Docker Plugins 
       - Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint 
   - Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well 

 ## Sprint 37 

 Dates: Friday May 11, 2018- Thursday May 31,2018   
 Sprint Goals/Focus: Pulp 3 GA + Pulp 2   
 Notes 

   - Reserve time for fixing issues found after Core Beta released 
   - Planning for conferences and Pulp 3.0 GA planning 

 Completion 

   - Lazy Sync planning completed 

 ## Sprint 36 

 Dates: Friday April 20, 2018- Thursday May 10,2018   
 Sprint Goals/Focus: Pulp 3 Core Beta   
 Notes 

   - Items focused on remaining Pulp 3.0 Core Beta deliverables 
   - Reserve time for fixing issues found after Core Beta released 
   - Planning for conferences and Pulp 3.0 GA planning 

 ## Sprint 35 

 Dates: Friday March 30, 2018- Thursday April 19,2018   
 Sprint Goals/Focus: Pulp 3 Core Beta   
 Notes 

   - Items focused on Pulp 3.0 Core Beta deliverables 

 ## Sprint 34 

 Dates: Friday March 9, 2018- Thursday March 29,2018   
 Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze   
 Notes 

   - Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint.  
   - Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag" 
   - Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.