Sprint Plans » History » Revision 16
Revision 15 (rchan, 07/06/2018 09:50 PM) → Revision 16/182 (rchan, 07/06/2018 10:02 PM)
# Sprint Plans
## Sprint 40
Dates: Friday July 13, 2018 - Thursday August 2, 2018
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA
Notes
- Pulp 2 bugs/features:
- Pulp 2.17 features:
- Rich Dependency Support
- Advanced Modularity
- Container/Docker plugin enhancements (3137)
- Core GA Features:
- CLI progress - feedback from July 2 deadline digested
- Lazy sync start
- Pending Versions - \<what progress can we make here\>
- Installer work on sprint - no commitment from core team on staffing
- Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
\<please make comments here\>
performance bugs
## Sprint 39
Dates: Friday June 22, 2018 - Thursday July 12, 2018
Sprint Goals/Focus: Pulp 2 + Pulp 3 GA
Notes
- Pulp 2 bugs/features:
- FIPS - can we aim to close all known stories that aren't blocked?
- Pulp 2.17 features:
- Advanced Modularity + Rich Dependency Support
- Container/Docker plugin enhancements
- Core GA Features:
- Installer work on sprint - no commitment from core team on staffing
- Trickle progress (whatever staffing allows after Pulp 2 commitments delivered) on Pulp 3 RPM and Docker Plugins
- CLI progress blocked - waiting on feedback period ending July 2, little progress made until feedback is received & digested
- Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well but would welcome community contribution
## Sprint 38
Dates: Friday June 1, 2018 - Thursday June 21, 2018
Sprint Goals/Focus: Pulp 3 GA + Pulp 2
Notes
- Pulp 2 bugs/features:
- FIPS
- Modularity
- Container/Docker plugin enhancements
- Core GA Features:
- Installerwork on sprint - no commitment from core team on staffing
- Pause progress on Pulp 3 RPM and Docker Plugins
- Only one Pulp3 Docker Plugin task - and probably will not get to this in this sprint
- Lazy sync ready to start from planning perspective, but no capacity, so this is paused as well
## Sprint 37
Dates: Friday May 11, 2018- Thursday May 31,2018
Sprint Goals/Focus: Pulp 3 GA + Pulp 2
Notes
- Reserve time for fixing issues found after Core Beta released
- Planning for conferences and Pulp 3.0 GA planning
Completion
- Lazy Sync planning completed
## Sprint 36
Dates: Friday April 20, 2018- Thursday May 10,2018
Sprint Goals/Focus: Pulp 3 Core Beta
Notes
- Items focused on remaining Pulp 3.0 Core Beta deliverables
- Reserve time for fixing issues found after Core Beta released
- Planning for conferences and Pulp 3.0 GA planning
## Sprint 35
Dates: Friday March 30, 2018- Thursday April 19,2018
Sprint Goals/Focus: Pulp 3 Core Beta
Notes
- Items focused on Pulp 3.0 Core Beta deliverables
## Sprint 34
Dates: Friday March 9, 2018- Thursday March 29,2018
Sprint Goals/Focus: Pulp 3 Core Beta Dev Freeze
Notes
- Moving to use Sprint Custom field instead of "Sprint/Milestone" field this sprint.
- Items not needing to be done by March 22 (Core Beta or otherwise) will be put on the sprint and keep "Sprint Candidate flag"
- Originally planned to end 3/22 for a feature freeze. Feature freeze was moved to 3/29 and didn't catch this update unilt 3/28/18.