Release Schedule » History » Revision 4

« Previous | Revision 4/86 (diff) | Next »
rbarlow, 03/21/2016 03:09 AM


[Draft] Pulp 2.9 Release Schedule

2016-05-17 2.9 branches created Build system adapted to build from branches
2016-05-24 2.9.0 Alpha Feature freeze, no new features after this
2016-06-07 2.9.0 Beta Freeze Only critical bug fixes after this
2016-06-14 2.9.0 Beta
2016-06-21 2.9.0 Release candidate Final Freeze
2016-06-28 2.9.0 Release

[Draft] Definitions

Alpha - All feature code changes for this release have been merged
Beta - All bug fixes that need to be in the release are complete. Dev believes the release is ready.
Release candidate - QE has performed their testing and is satisfied to release.

Updated by rbarlow over 8 years ago · 4 revisions