[Draft] Pulp 2.9 Release Schedule¶
2016-05-17 | 2.9 branches created | Build system adapted to build from branches |
2016-05-24 | 2.9.0 Alpha | Feature freeze, no new features after this |
2016-06-07 | 2.9.0 Beta Freeze | Only critical bug fixes after this |
2016-06-14 | 2.9.0 Beta | |
2016-06-21 | 2.9.0 Release candidate | Final Freeze |
2016-06-28 | 2.9.0 Release |
[Draft] Definitions¶
Alpha - All feature code changes for this release have been merged
Beta - All bug fixes that need to be in the release are complete. Dev believes the release is ready.
Release candidate - QE has performed their testing and is satisfied to release.