# 2.18.0 Release Schedule
2 1 dkliban@redhat.com
3 13 ttereshc
The current tentative release date for 2.18.0 is November 27, 2018
4 1 dkliban@redhat.com
5
## Checklist
6
7
The first item on the list **not** struck through is in progress.
8 10 dkliban@redhat.com
9
  - Dev Freeze date 
10 1 dkliban@redhat.com
      - November 6, 2018
11 12 ttereshc
  - Beta Build date.
12
      - November 13, 2018
13 11 ttereshc
      - - Targeting all content here: https://pulp.plan.io/versions/64\<?\>
14 10 dkliban@redhat.com
  - Prerequisites to building:
15
      - Issues blocking release
16
      - No procedural issues blocking this release (broken CI env, and similar)
17
  - waiting period (1 week after beta release date) before RC
18 12 ttereshc
      - RC Date: November 20, 2018
19 10 dkliban@redhat.com
  - waiting period (1 week after RC release date) before GA
20 12 ttereshc
      - GA Date: November 27, 2018
21 10 dkliban@redhat.com
  - verify [issues with](https://pulp.plan.io/issues?utf8=%E2%9C%93&set_filter=1&f%5B%5D=cf_4&op%5Bcf_4%5D=%3D&v%5Bcf_4%5D%5B%5D=2.19.0&f%5B%5D=cf_36&op%5Bcf_36%5D=%3D&v%5Bcf_36%5D%5B%5D=1&f%5B%5D=&c%5B%5D=project&c%5B%5D=tracker&c%5B%5D=status&c%5B%5D=priority&c%5B%5D=cf_5&c%5B%5D=subject&c%5B%5D=author&c%5B%5D=assigned_to&c%5B%5D=cf_3&c%5B%5D=cf_4&group_by=project&t%5B%5D=) "verification required" set
22
23
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 2.18.0 release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.
24
25
If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available November 20, 2018. This page will be updated as progress is made.
26
27
Release Contact: tbd on freenode (#pulp and#pulp-dev)