# 2.18.0 Release Schedule
2 1 dkliban@redhat.com
3 10 dkliban@redhat.com
The current tentative release date for 2.18.0 is November 20, 2018
4 1 dkliban@redhat.com
5
## Checklist
6
7
The first item on the list **not** struck through is in progress.
8 10 dkliban@redhat.com
9
  - Dev Freeze date 
10
      - October 30, 2018
11
  - Beta Build date.
12
      - November 6, 2018
13
      - - Targeting all content here: https://pulp.plan.io/versions/\<?\>
14
  - Prerequisites to building:
15
      - Issues blocking release
16
      - No procedural issues blocking this release (broken CI env, and similar)
17
  - waiting period (1 week after beta release date) before RC
18
      - RC Date: November 13, 2018
19
  - waiting period (1 week after RC release date) before GA
20
      - GA Date: November 20, 2018
21
  - verify [issues with](https://pulp.plan.io/issues?utf8=%E2%9C%93&set_filter=1&f%5B%5D=cf_4&op%5Bcf_4%5D=%3D&v%5Bcf_4%5D%5B%5D=2.19.0&f%5B%5D=cf_36&op%5Bcf_36%5D=%3D&v%5Bcf_36%5D%5B%5D=1&f%5B%5D=&c%5B%5D=project&c%5B%5D=tracker&c%5B%5D=status&c%5B%5D=priority&c%5B%5D=cf_5&c%5B%5D=subject&c%5B%5D=author&c%5B%5D=assigned_to&c%5B%5D=cf_3&c%5B%5D=cf_4&group_by=project&t%5B%5D=) "verification required" set
22
23
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 2.18.0 release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.
24
25
If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available November 20, 2018. This page will be updated as progress is made.
26
27
Release Contact: tbd on freenode (#pulp and#pulp-dev)