# 2.18.0 Release Schedule
2
3
The current tentative release date for 2.18.0 is October 9, 2018
4
5
## Checklist
6
7
The first item on the list **not** struck through is in progress.
8
9
  - Dev Freeze date 
10
      - September 18, 2018
11
  - Beta Build date.
12
      - September 25, 2018
13
  - Prerequisites to building:
14
      - Issues blocking release
15
      - No procedural issues blocking this release (broken CI env, and similar)
16
  - waiting period (1 week after beta release date) before RC
17
      - RC Date: October 2, 2018
18
  - waiting period (1 week after RC release date) before GA
19
      - GA Date: October 9, 2018
20
  - verify [issues with](https://pulp.plan.io/issues?utf8=%E2%9C%93&set_filter=1&f%5B%5D=cf_4&op%5Bcf_4%5D=%3D&v%5Bcf_4%5D%5B%5D=2.18.0&f%5B%5D=cf_36&op%5Bcf_36%5D=%3D&v%5Bcf_36%5D%5B%5D=1&f%5B%5D=&c%5B%5D=project&c%5B%5D=tracker&c%5B%5D=status&c%5B%5D=priority&c%5B%5D=cf_5&c%5B%5D=subject&c%5B%5D=author&c%5B%5D=assigned_to&c%5B%5D=cf_3&c%5B%5D=cf_4&group_by=project&t%5B%5D=) "verification required" set
21
22
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the 2.18.0 release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.
23
24
If all goes well, and no blocking bugs delay further release stages, this release should become Generally Available October 9, 2018. This page will be updated as progress is made.
25
26
Release Contact: dkliban on freenode (#pulp and#pulp-dev)