# 2.14.1 Release Status
2
3
## Checklist
4
5
The first item on the list **not** struck through is in progress.
6
7
  - Beta Build date (tentative)
8 4 pcreech
      - ~~September 12, 2017~~ (delayed by 2.13.4's delay)
9 6 pcreech
      - ~~September 19, 2017~~ (delayed again by 2.13.4)
10 7 pcreech
      - September 27, 2017
11 1 pcreech
  - Prerequisites to building:
12 8 pcreech
      - ~~No open issues blocking this release~~
13
      - ~~Issues with the "verification required" field set verified.~~
14
      - ~~No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar)~~
15
  - ~~test scratch build from beta branch~~
16
      - ~~Automated test results approved by QE~~
17
  - ~~Beta 1 Released~~
18
      - ~~waiting period (1 week after beta 1 release date) before GA is allowed~~
19 1 pcreech
  - Generally Available
20 8 pcreech
      - October 05, 2017
21 1 pcreech
22
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.