# 2.14.1 Release Status
2
3
## Checklist
4
5
The first item on the list **not** struck through is in progress.
6
7
  - Beta Build date (tentative)
8 4 pcreech
      - ~~September 12, 2017~~ (delayed by 2.13.4's delay)
9 6 pcreech
      - ~~September 19, 2017~~ (delayed again by 2.13.4)
10 7 pcreech
      - September 27, 2017
11 1 pcreech
  - Prerequisites to building:
12
      - No open issues blocking this release
13
      - Issues with the "verification required" field set verified.
14
      - No procedural issues blocking this release (such as merge-forward issues, broken CI env, and similar)
15
  - test scratch build from beta branch
16
      - Automated test results approved by QE
17
  - Beta 1 Released
18
      - waiting period (1 week after beta 1 release date) before GA is allowed
19
  - Generally Available
20 7 pcreech
      - October 04, 2017
21 1 pcreech
22
The rest of the checklist is conditional on whether or not blockers are found in the beta cycle; this page will be updated as the release progresses. See the [[Release Schedule#Release-Stage-Conditions]] for more details.